Construction Information

 

 As Construction Concludes, we prepare for a new era of quality
senior healthcare service to Chattanooga. 
Stop by and see us.

July 5, 2007:  Ready for furniture Delivery...
 
Cubical Installation underway                                    Main Lobby Reception Desk Installed.
 
View of Connector to Siskin Hospital (left) and side view of finished exterior (right)

June 11, 2007:  Building Dedication  (Photos Courtesy of  Wesley Schultz)

   
 
 

May 19, 2007  May Aerial Shot

May 17, 2007  The difference a few hours makes...
 

May 15, 2007    Exterior Panel Install Begins...
 

May 14, 2007
   
Dining/Activity Flooring Installed                                View Hallway Floor Finishes

May 4, 2007:  Finish Work Well Underway
 
Ceiling Grid ready for tiles in Parking Garage                (Right)  Recessed Lighted Coves on First Floor
 
Resident Bathroom Cabinetry                                 Resident Room Dresser and Desk Area

 
Hallway flooring installation underway                            2nd Floor Nursing and Community Gathering Area

April 24, 2007
 
Green Green "Grass" of Home?                                 (R) Day Spa Flooring Installed Today
 First View of Coves on First Floor Ceiling!

April 19, 2007      Flooring install begins...
 

April 17, 2007

 
Bathroom accessory installation well underway...               Door hanging commences today.

April 12, 2007
 
Shower / Whirlpool Room Tile Installation                            This is Blaine from Liberty Enterprises wanting to    
                                                                                         give a shout out to all of his internet fan base.

April 10, 2007
 
Glass added to Vestibule Entryway                            Dirt Added for Front Landscaping

April 4, 2007
 
Window Mullions Added to Entryway                       Celing Grid Begins in Patient Rooms

 Departmental Leadership gets first glimpse.

March 22, 2007
 
Paint finishes begin.                                                  Tile to resident bathrooms.

March 19, 2007: Aerial Photo

March 7, 2007
 
View of the storefront installed                                   Elevator car being assembled

 
View of Windows on Adminstrative Floor   
                
                            2nd Floor Wall "Mudding" underway

February 26, 2007

View of Nursing Home in reflection of the windows of Siskin Hospital

February 22, 2007
 
(L) Storefront installed to activity/dining        (R) Preparing to pave under the connector
areas

February 19, 2007: Aerial shot

February 11, 2007: Connector structural steel in place!
 
(L) View from back of 1st floor through to the hospital; (R) View of connector from ground

February 8, 2007
 
(L) Elevator installation underway; (R) Entryway curb and gutter forms in place

February 7, 2007
 
(L) C-Channels in place to elevate floor for connector to hospital; (R) Radius hallway walls take shape

January 22, 2007: Let the drywalling begin...
 

January 20, 2007: Aerial shot

January 18, 2007
 
Glass in place on both sides of sequence #1

January 17, 2007
 Drywall delivered to all rooms in Seq. #1

January 15, 2007
 
Roof fully installed and glass commenced on second floor

January 10, 2007
 
(L) Window rrames stacked for install; (R) First frames installed in Seq. #1

January 2, 2007
 
Exterior sheeting to front of building                           Sun rises on new roof to Seq. #1

December 15, 2006:Aerial photographs

 
READY FOR GLASS

December 11, 2006
 
Densiglass installation commences                        Typical conduit for one pt. room wall

December 6, 2006
    View of completed roof and air units                                        Core drilling for plumbing

 
View of main elevator shaft                                                                   Glass arrives!

November 22, 2006: A view from the roof... only a few planks remaining


November 21, 2006: Aerial Shot, roof install in progress...

November 20, 2006: "Roof Week"

Concrete pour to parking deck                      Setting roof planks to 3rd floor

 
View from Sequence #1                             Patient floor central lobby area

November 6, 2006

Sequence #1 roof started; (R) Serpentine cooridor wall track added to ceiling.

November 2, 2006
 
Sequence #1 roof installed                                              Sequence #3 topping poured

 
(L) First floor administrative offices                                          (R) Exterior radius wall

October 26, 2006
 
3rd floor completion                                                                      Final pieces placed

October 20, 20006: Aerial shot shows completed 1st and 2nd floors and partial 3rd floor installed

October 18, 2006
  First floor offices take shape                                   Front entrance curb ready to pour

October 13, 2006
 
(L) Marking the radius (curved) walls in the first floor connector
(R) Installing the first set of pan stairs in Sequence #3 stairwell

 
Forming curved radius in front entryway          Third floor Seq. 2 hollowcore install

October 11, 2006
 
Sequence #3 metal stud commences; (R) Edge angle connects sequence 1 & 2 third floor

October 9, 2006
 
Pouring 2" topping on first floor; (R) Spraying fireproofing exposed beams above 1st floor parking deck

October 3, 2006
 
Third floor added to Sequence #1                             Sequence #2 stud work continues

September 28, 2006
 
Second floor hollowcore complete; (R) Sequence #1 load-bearing metal stud progress.  Sequence #2 has started, as well (upper left)

September 25, 2006
 Test panel of the exterior finish

September 20, 2006: Aerial Shot

 
Edge angle added to Sequence #3                               2" topping poured on Seq #2

September 13, 2006
 
Load-bearing metal stud work begins on 2nd floor and hollowcore added to Seq. #2

September 11, 2006
  (L) Edge detail added to Sequence #3: (R) Load-bearing stud ready on second floor

September 7, 2006
 
View from 2nd floor (w/topping poured); (R) View from back of 1st floor (ductwork started)

August 31, 2006

Stairway "pans" delivered                  Blocking the ground floor, Sequence #1

August 26, 2006
 
Adding temporary stairs to Sequence #1 
  
August 25, 2006
 
Hollow core placement continues; (R) Close up view of 1st floor parking entrance

August 24, 2006
 
Edge detail "The Wave" added to 2nd floor               Sequence #2 hollowcore installed

August 18, 2006

August Aerial Shot

August 17, 2006
 
2nd floor hollowcore in Sequence #1                   Steel work continues on Sequence #3

August 16, 2006
 
Second floor taking shape

Retaining wall around Sequence #3

August 11, 2006
  Hollowcore finished in Seq. #1                                 Structural Steel Completed Seq. #2
August 10, 2006

View into office area (from road)                               Sequence #2 steel commences

August 9, 2006
HOLLOWCORE CONCRETE ARRIVES FOR THE FLOORS!  Sequence #1


The first hollowcore plank is installed                            Hollowcore for 1st floor

August 7, 2006

 
HOT! High of 95 today. Fan and shade to provide relief; (R) Finishing stone backfill

 
The steel garden                                                         Ground floor pours start

August 4, 2006
 
Sequence #2 structural steel taking shape; (R) "Keystone" retaining wall around Seq. #2

 
View of Sequence #2 in progress (note columns by retaining wall): (R) Steel with concrete wraps in Sequence #1

August 3, 2006
 
Compressing block behind retaining wall; (R) Setting keystone block retaining wall

 
Side View of Section #2 steel erection; (R) Columns prepped for concrete (Sec. #1)

July 27, 2006
 
View up the Seq. #1 stairwell; (R) Main elevator blockwork in progress


  Waterproofing retaining wall

July 26,2006

View of "Sequence 1" from construction trailer. Stairwell complete to roof access.

July 24, 2006
 
View of Sequence 1 steel work from the hospital connector location; (R) Mason work begins with the "cornerstone" placed.

July 21, 2006
   
Sequence 1 structural steel continues; (R) Pouring footing for main elevator bank - 100 yards!

July 20, 2006: The building starts to take shape

July 19, 2006:  STRUCTURAL STEEL ARRIVES!
   
Transformer set in place         Steel arrives on flatbed         Beams unloaded by crane

  First pieces of steel are erected

July 18, 2006: Aerial photo of site

July 14, 2006
 
Paving north side of site to use as a laydown area througout construction

July 10, 2006
   
(L) Poured retaining wall completed; (C) Sequence #2 spread footings start

July 7, 2006
   
(L) Marking footing location for 2nd elevator pit; (C) Spread footings in bottom of "T" ready for structural steel; (R) Pouring retaining wall: 77 yards of concrete (gross weight: >127 tons!)

July 3, 2006
   
(L & C) Forms being installed for west retaining wall (16 feet high)
(R) Yes, hot day today...find the shade wherever you can...

 

June 29, 2006
   
(L) Digging the "fire pit" (water connection); (C) Elevator support columns;
(R) Inside a typical spread footing pit.

June 28, 2006
  Footer poured for retaining wall.

June 27, 2006
 
Preparing to pour the footing for the retaining wall on the west (front) of the building

June 21, 2006
   
(L) Preparing for spread footings: (C) Re-bar ready for installation in
spread footings; (R) New opened parking lot in use on southeast corner

June 16, 2006: "If you pave it...they will park"
   
New outpatient parking area will ease congestion with additional 41 spaces during
construction; (R) Re-bar unloaded for spread footings as retaining wall excavation continues in background

June 15, 2006: North side parking paving day!
 
(L) 2" Binder core is installed for Siskin Hospital parking during construction of building
(R) Further excavation on hillside for the main retaining wall location.

June 8, 2006
   
(L) Undercut holes compressed with remote control roller; (C) 6" of "PUG" rock installed in prep for asphalt; (R)  More unsuitable soils require undercutting and replacement with rock

June 5, 2006
 
Rig for digging GeoPiers (#136 to drill). Augur bit (R) used to drill hole
approx 20 ft deep, then rock inserted and power tamped down in 1 foot
high sections until ground level reached. The spread concrete footings will
essentially rest on these columns ("piers") of compressed rock.

 

June 1, 2006
 
(L) Typical layout for GeoPier footings: (R) Trench for roof drains

May 30, 2006
 
 
Unsuitable soils were encountered on buliding pad; need to "undercut" and replace with fill stone. (R) Example of undercut "pit" shown in photo 

May 23, 2006
 
A level bulding pad is prepped for deep foundations; (R) Remaining dirt removal

May 15, 2006
 
Utility sitework continues; (R) Valet parking staff ready to assist patient parking needs with a smile

May 10, 2006
 
(L) Storm drains are installed; (R) A construction progress poster is mounted to keep
the residents/staff informed of the sights and development

May 5, 2006
 
(L) Site leveling progress; (R) Gravel hauled in for storm drain installation over the weekend

May 3, 2006
 

Backfill begins to level the surface; (R) Site utility materials moved into place for install

 
(L) Striping the entry drive to the hospital to improve traffic flow; (R) Site leveling continues

May 1, 2006
 
Primary cut now runs the full length of the front facade of the building

April 28, 2006

 
Southwest excavation contines; (R) Site utility manholes ready for install

April 26, 2006

Excavation begins                                                    Cut is started on southwest corner

April 24, 2006

Parking lot removal is completed, job sign is posted.

April 20, 2006

Additional parking added to ease congestion

April 19, 2006
 
Aerial shot of construction site

April 17, 2006

Parking lot extraction begins...

April 12, 2006

Siskin Hospital parking lot is prepared for the excavation stage


Electric Power Board grants temporary easment for construction parking and laydown area across the street from the construction site

Click here for Groundbreaking Overview (March 15, 2006) (.pdf)